|
| |
Incident Report -
Communications Lapse and Above-Standard Dust Readings - August 4, 2008
On Monday, August 4, 2008, a communications lapse
occurred when the contractor (SCE) did not notify AGC that excavation of topsoil
over battery casings would occur. This excavation was performed to allow SCE to
pump water from the existing basin as allowed in the 100% Design. Even though
the action is something that is allowed, AGC needed to have air monitors set up
prior to movement of contaminated soils, so that the effectiveness of the dust
control measures could be monitored. The delay was very brief because AGC people
onsite saw the excavation and set up the monitors within minutes. Nonetheless,
this was the second communications lapse within a week, and shows that further
work is still needed on site communications.
In the daily operations meeting later on Monday (as well as in earlier
discussions after the excavation occurred), the importance of communicating
these types of changes in site activities was stressed.
When the air monitors were set up, the excavation was already completed and the
pumping of water was taking place. The air monitors recorded particulate matter
(e.g., dust) slightly in excess of the relevant performance standard for
excavation of battery casing material contained in the 100% Design. It was
determined that no corrective action was necessary based on several factors:
· The above-standard readings were observed prior to when the instrument was
fully stabilized, so they may not be representative of the actual conditions at
the time.
· There was no visible dust.
· The excavation had occurred through wet soils, decreasing the chance of dust
being released.
· The readings upwind of the excavation were also slightly elevated.
Review of the data at the end of the day indicated that there were some half
hour averages that were above the standard that were measured when there was no
excavation taking place, only pumping of water. The performance standard for
when battery casings are excavated is extremely low. As in this case, the
performance standard can
sometimes be below the level of dust in upwind samples – that is, dust having
nothing to do with site activities. So a brief reading that is over this
standard is neither unexpected nor alarming and may not warrant a change in how
work is being performed. It is a measure of the extreme care that will be taken
when excavating these materials. We are continuing to review the standards as
well as the equipment used to measure them and evaluating how the work is being
performed in order to complete the excavations in a safe manner.
Throop Borough was notified of both the communications lapse and the
above-standard dust readings.
Page Last Modified
Thursday November 12, 2009 12:32:09 PM
|