|
| |
Incident Report -
Discharge of Muddy Water Into Sulphur Creek - July 28, 2008
On July 28, 2008, muddy water was discharged from
the Marjol site into Sulphur Creek. The discharge lasted for about a half hour
to forty minutes and was in violation of site procedures. Fortunately, the water
that was discharged, although muddy, was from the new basin which is only
collecting water from areas of the Site that are not contaminated. AGC collected
two sediment samples at the location where the basin water discharges into
Sulphur Creek. The two samples had lead readings that were below the detection
limit of the instrument so there is no evidence of a release of
lead-contaminated sediment into the river. A sample was taken in the river for
confirmation following the protocols in the design but the results of the lead
analysis have not been received yet. Throop Borough also tested the sediments in
Sulphur Creek but those results aren’t available yet either.
Even though the discharge was from clean areas, the incident should not have
occurred, and Throop Borough should have been contacted sooner. These are both
significant errors that called for reconsideration of site procedures.
Gould voluntarily shut down construction operations at the Site on Wednesday,
July 30, 2008, in order that the incident which occurred could be properly
addressed. A meeting was held on Thursday, July 31, 2008, to discuss the
incident and develop a set of procedures such that this type of incident does
not happen again in the future. Representatives from Gould, AGC, SCE, PADEP,
USEPA, Throop Borough, Representative Frank Andrews Shimkus, and members of the
press were in attendance at the meeting.
At the meeting, AGC reviewed the measures that Gould, AGC and SCE proposed to
prevent any such incident from happening again.
● Directives to stop
an activity will be given visually as well as orally using a handwritten
“STOP”, flag or pre-determined signal.
● Daily
operational meetings will be held to discuss the next day’s work and develop
contingency plans in the event that something unexpected happens.
● If an
established procedure is modified, then a test run will be conducted to
ensure that the modified procedure will accomplish the objectives.
Changes were made on SCE’s on-site personnel as
well to improve internal communications and communications with AGC. Changes
were also made in AGC staffing and procedures at the site to emphasize the need
to inform Borough officials immediately of any unexpected event of possible
public concern.
Both USEPA and PADEP stated that they did not have a problem with work resuming
on Friday, August 1, 2008. PADEP required that a detailed report on the
incident be provided to it, and they are conducting their own investigation.
(Click here to review the NPDES non-compliance report on
the incident.) Throop Borough has been
provided a copy of the report.
(Click the dates below to read articles and an editorial from the
Scranton Times.)
-
Article, July
30, 2008
-
Article, July
31, 2008
-
Article,
August 1, 2008
-
Editorial, August 1, 2008
Page Last Modified
Thursday November 12, 2009 12:32:09 PM
|