| |||||
|
Construction Schedule and Information
Weekly Construction Schedule - November 20, 2009 to November 26, 2009
Stained Soils in Excavation Area O
In December of 2008, an
approximately 5-foot deep sump or shallow well with an organic (similar to
diesel fuel or gasoline) odor was encountered in the excavation area (Area
O). The area of the sump was secured for the winter months and on May 1,
2009, the contractor resumed excavations in that area. As of October 23, 2009, Gould estimates that implementation of the Final Remedy at the Marjol Battery Site is approximately 85% complete. EXCAVATION NEARLY COMPLETE - The excavation of contaminated material is expected to be completed by October 23, 2009 except for sediment in Area B that was affected by stormwater management (stormwater from the Containment Area or cap area was pumped into Area B to prevent additional overflows of water from the Containment Area). Testing of sediment in the basin has shown that some sediment from the basin will also need to be handled as contaminated material before solidification is complete in the CA. These areas should be complete by October 30, 2009. STATUS OF SOLIDIFICATION – The bottom layer of the CA is a solidified layer comprised of three separate 9-inch lifts of solidified material. As of October 23, 2009, solidification is about 70% complete. Off-site sources of clean fill will be used for solidification for the third lift across the entire CA and on the steep slopes because there was an insufficient volume of contaminated soil in Area H for all three lifts of solidified material. Mixing of the clean fill with lime kiln dust is occurring off-site so that the mixed material can be placed and compacted as it is brought on-site. Solidification will be ongoing into November 2009 using both a machine on-site (called a Stehr) to solidify the lifts of contaminated soils that have been placed in the CA, and by bringing clean fill that is already mixed with lime kiln dust to the site and placing it. The compaction requirements and the performance standards for the solidified material are the same for both solidification methods. OFF-SITE VERIFICATION SAMPLING - Once the excavation of contaminated materials is completed, the second phase of the off-site verification sampling will take place. Off-site verification sampling was performed prior to and will be performed following remedial activities to confirm that remedial activities did not cause off-site contamination. Five locations were sampled in areas that were previously remediated. A total of 20 samples were collected from each location during the pre-construction sampling. Ten samples from each location were sent to a lab and analyzed and the remaining ten samples were archived for future analysis if required. The same procedures will be followed for the second phase of testing. INSTALLATION OF GEOSYNTHETICS (PLASTIC LAYERS OF THE CAP) – Once the solidified layer on the cap is completed, the next step is installation of the geosynthetic layers. A decision on whether to proceed with at least part of the installation of the geosynthetics this fall will be made in November 2009. If the geosynthetic installation is postponed until spring, all exposed, loose soils will be seeded and protected with either straw, jute matting or temporary erosion control mat depending on the slopes. Within the CA, all contaminated materials will be covered with at least one 9-inch lift of uncontaminated, solidified material, so there will not be any contaminated material at the surface of the Site.
We are using Throop Borough’s 48-acre property as our primary fill source. Throop Borough and Gould have agreed that Gould will use the material from the 48 acres as backfill material on the Site. Using this material is a benefit to everyone. By removing fill from the Borough’s 48-acre property, the Borough is getting some necessary grading work done in preparation for future construction activities (a proposed park) that may take place on the property. Gould has also agreed to install the base for a roadway along the haul road that will be used so that the Borough will eventually have a secondary access route to its 48-acre property. The greatest advantage of using the Borough’s fill is that the trucks bringing the fill into the Site will not have to run on Borough roads. The fill material from the borough property is a residue from prior mining called “red ash.” An NPDES permit from Lackawanna County and a regulated fill permit from PADEP were required and obtained without difficulty. The fill material has no connection with the Marjol lead operations, and is not contaminated with lead.
A haul road was constructed from the Borough’s
48-acre property to the Marjol site through the North Woods. Work on the
Borough’s 48-acre property and on the haul road is being conducted similar to any
uncontaminated construction site where dust is controlled as a nuisance. The “No
Visible Dust Rule” that is in effect on the Marjol Site is not in effect on
the haul road or on the Borough’s property as these areas are not contaminated
with lead. Trucks will still use Delaware Street to bring in topsoil, stone, geosynthetics for the cap, and other items, but using the Borough’s 48 acres as
a fill source has significantly reduced the number of trucks that have to
traverse Delaware Street. Here is some basic information that may answer
some of your important questions on how construction will affect those of you
living near the Marjol Site: 1) When will construction start and when will it end? The construction work began on May 12, 2008 and is currently projected to be completed by the end of November 2009. However, the construction schedule depends on many factors, including the amount of contaminated material in each excavation area (if it is greater/less than what is expected based on testing) and of course, the weather. At this time, we do not know yet whether we will need to go into a third construction season in spring 2010. Our priority is to make sure the work gets done carefully and completely, more so than keeping to the original schedule. We will continue to provide construction information on this page as the 2009 season proceeds. All reasonable effort is being made to keep the traffic on Throop Borough roads to a minimum; however as with any construction site, there will be trucks, workers' vehicles and the noise of the equipment on-site. When we expect a period of high construction activity, with more than the usual amount of trucks and noise, we will tell people the expected dates on this page.
3) What will the working hours be? Working hours will be from approximately 6:30 AM to 4:30 PM Monday through Friday (with the possibility of working until 7 pm when needed) and on Saturday, from approximately 6:30 AM to 2:30 PM. These days and times are consistent with Throop Borough ordinances. |
|