Marjol Battery Site
**CAUTION**  Use of fill material from Throop Borough’s 48-acre property will resume this week.  For safety purposes, we ask residents to stay out of this area during construction activities. **CAUTION** 
 
Home

Site Background

Summary of Corrective Measures Implementation (CMI) Process

Construction Schedule and Information

Final (100%) Remedial Design

Air Data

Stormwater Management System

Photo Gallery

Quarterly Progress Reports & Monitoring

Community Relations

Documents

FAQs

Contact Us

Web Site Map

Construction Schedule and Information

Weekly Construction Schedule - October 30, 2009 to November 5, 2009

Weekly

Project Schedule

& Remediation Activities

Last Updated: October 29, 2009

 

 

Notes: Items that we think residents might be particularly interested in are highlighted in orange.

 

1) The solidified layer for the cap (bottom layer) will be made by mixing soils from the last area being

excavated with a cement like material called lime kiln dust.  The mixture will be placed in the

Containment Area in layers and compacted where it will become “solidified” by gaining strength

through the soil particles sticking together.   The lime kiln dust is a white powder-like material; it is

not contaminated with lead.   Every effort will be made to adhere to the zero dust policy at the Site

even with the lime kiln dust, but during the solidification process, it is possible that you might see

small localized areas of white dust.  Air monitoring will continue during the solidification process. 

Period Covered:

Planned Activities 

Expected Off-Site Impact

 

October 30, 2009 to November 5, 2009

 

 

 

             

      

·         Spreading of material from excavation Area H in the CA.

 

 

 

 

·         Solidification in the CA using the Stehr machine to mix the lime kiln dust (LKD) in with the contaminated soils to be solidified. 

 

 

  

 

·         Import and placement (in the CA) of clean solidified material that is being mixed with LKD at the off-site source location.

 

 

 

 

 

·         Excavation of material from Throop Borough’s borrow source property for backfilling of excavation Area H.

 

 

 

 

 

  

 

  

 

·         Importing of cap cover soil for the cap area.

 

 

 

 

 

  

 

·         Dewatering of the sedimentation basin. 

 

 

 

 

 

 

·         Seeding and stabilization as necessary across the Site to obtain good vegetative growth.  

 

 

 

    

·         Survey of Area H bottom of excavation and the top of waste in the final section of the CA.   

 

  

 

 

 

  

·         Residents may hear the back up alarms and the sound of the equipment running.

 

 

 

·         See information above under “Notes” regarding solidification.  Residents may hear the back up alarms and the sound of the equipment running.

 

 

 

 

 

·         See information above under “Notes” regarding solidification.  Trucks importing soils mixed with lime kiln dust to the Site will be entering the Site through the Delaware Street gate.

 

 

 

 

·         Residents may see the employees working on the 48-acre property and will likely hear the back up alarms and the sound of the equipment running.  Residents are asked to stay out of the work areas for safety reasons.  At the Site, residents may see the equipment and hear the back up alarms and the sound of the equipment running.  

 

 

 

·         Trucks importing cap cover soil to the Site will be entering the Site through the Delaware Street gate.  If there are more than 12 trucks per hour, a flag person will be present at the corner of Delaware and Franko Streets.

 

·         None.

 

 

 

·         None.

 

 

 

 

 

 

 

·         None.

              

 

 

 

Stained Soils in Excavation Area O

In December of 2008, an approximately 5-foot deep sump or shallow well with an organic (similar to diesel fuel or gasoline) odor was encountered in the excavation area (Area O). The area of the sump was secured for the winter months and on May 1, 2009, the contractor resumed excavations in that area.

Once the sump itself was removed, it was determined that the soils in the vicinity of the sump were stained and had an organic odor. Excavations of these soils encompassed an area of about 140’ by 75’ and extended to a depth of 30’ in one area. The soils were right next to and below the location of the former office and maintenance building. The excavated soils were placed in stockpiles within the Containment Area where the soils will be further tested to determine whether the material can be placed permanently in the Containment Area. Two stockpiles are present: one containing soils with detectable levels of volatile organics and lead levels above the performance standard (500 ppm) and the second pile containing soils only with detectable levels of volatile organics and no lead contamination.

A sampling instrument called a geoprobe was brought in to try to delineate the vertical and horizontal extent of the volatile organics in the soil.  Geoprobes combined with screening of the soils with a PID to detect the presence of volatile organic compounds found that the residual contamination is likely present within the weathered rock zone. Further excavation or characterization was determined to be impractical without significantly impeding the lead clean-up, and the excavation was backfilled with the approval of the EPA and DEP so that restoration activities can could proceed in this area. Throop Borough was also informed of the plans to backfill the excavation by both EPA and Gould prior to the work taking place. A low permeability layer was placed within the backfill to minimize the infiltration of rain water into the former excavation. Gould has committed to submit a summary report presenting the analytical results and information on the excavation and the geoprobes to the agencies along with a proposal for follow-up activities to be conducted and a schedule for those activities.  An agency decision has not been made yet regarding what additional characterization and/or remediation of the volatile organics, if any, may be required.

 

Percent Completion of Project

As of October 23, 2009, Gould estimates that implementation of the Final Remedy at the Marjol Battery Site is approximately 85% complete. 

EXCAVATION NEARLY COMPLETE - The excavation of contaminated material is expected to be completed by October 23, 2009 except for sediment in Area B that was affected by stormwater management (stormwater from the Containment Area or cap area was pumped into Area B to prevent additional overflows of water from the Containment Area).  Testing of sediment in the basin has shown that some sediment  from the basin will also need  to be handled as contaminated material before solidification is complete in the CA.  These areas should be complete by October 30, 2009.

STATUS OF SOLIDIFICATION – The bottom layer of the CA is a solidified layer comprised of three separate 9-inch lifts of solidified material.  As of October 23, 2009, solidification is about 70% complete.  Off-site sources of clean fill will be used for solidification for the third lift across the entire CA and on the steep slopes because there was an insufficient volume of contaminated soil in Area H for all three lifts of solidified material.   Mixing of the clean fill with lime kiln dust is occurring off-site so that the mixed material can be placed and compacted as it is brought on-site.   

Solidification will be ongoing into November 2009 using both a machine on-site (called a Stehr) to solidify the lifts of contaminated soils that have been placed in the CA, and by bringing clean fill that is already mixed with lime kiln dust to the site and placing it.  The compaction requirements and the performance standards for the solidified material are the same for both solidification methods.

OFF-SITE VERIFICATION SAMPLING - Once the excavation of contaminated materials is completed, the second phase of the off-site verification sampling will take place.  Off-site verification sampling was performed prior to and will be performed following remedial activities to confirm that remedial activities did not cause off-site contamination.  Five locations were sampled in areas that were previously remediated.

A total of 20 samples were collected from each location during the pre-construction sampling.  Ten samples from each location were sent to a lab and analyzed and the remaining ten samples were archived for future analysis if required.  The same procedures will be followed for the second phase of testing.        

INSTALLATION OF GEOSYNTHETICS (PLASTIC LAYERS OF THE CAP) – Once the solidified layer on the cap is completed, the next step is installation of the geosynthetic layers.  A decision on whether to proceed with at least part of the installation of the geosynthetics this fall will be made in November  2009.  If the geosynthetic installation is postponed until spring, all exposed, loose soils will be seeded and protected with either straw, jute matting or temporary erosion control mat depending on the slopes.  Within the CA, all contaminated materials will be covered with at least one 9-inch lift of uncontaminated, solidified material, so there will not be any contaminated material at the surface of the Site. 

 

Throop Borough Fill Source

We are using Throop Borough’s 48-acre property as our primary fill source. Throop Borough and Gould have agreed that Gould will use the material from the 48 acres as backfill material on the Site. Using this material is a benefit to everyone. By removing fill from the Borough’s 48-acre property, the Borough is getting some necessary grading work done in preparation for future construction activities (a proposed park) that may take place on the property. Gould has also agreed to install the base for a roadway along the haul road that will be used so that the Borough will eventually have a secondary access route to its 48-acre property. The greatest advantage of using the Borough’s fill is that the trucks bringing the fill into the Site will not have to run on Borough roads.

The fill material from the borough property is a residue from prior mining called “red ash.” An NPDES permit from Lackawanna County and a regulated fill permit from PADEP were required and obtained without difficulty. The fill material has no connection with the Marjol lead operations, and is not contaminated with lead.

A haul road was constructed from the Borough’s 48-acre property to the Marjol site through the North Woods. Work on the Borough’s 48-acre property and on the haul road is being conducted similar to any uncontaminated construction site where dust is controlled as a nuisance. The “No Visible Dust Rule” that is in effect on the Marjol Site is not in effect on the haul road or on the Borough’s property as these areas are not contaminated with lead. Trucks will still use Delaware Street to bring in topsoil, stone, geosynthetics for the cap, and other items, but using the Borough’s 48 acres as a fill source has significantly reduced the number of trucks that have to traverse Delaware Street.

****CAUTION**** SAFETY ON HAUL ROAD AND THROOP BOROUGH”S FILL PROPERTY
We ask for your cooperation and understanding while fill is being imported from the Borough’s property. There are many large trucks traversing the haul road back and forth to the Site each day. For safety purposes, please keep yourself and your children off the haul road and away from the Borough’s 48 acre property throughout this process. For your safety, please stay away from the construction equipment and the construction activities.
 

Construction Information

Here is some basic information that may answer some of your important questions on how construction will affect those of you living near the Marjol Site:
 

1) When will construction start and when will it end?  

The construction work began on May 12, 2008 and is currently projected to be completed by the end of November 2009.  However, the construction schedule depends on many factors, including the amount of contaminated material in each excavation area (if it is greater/less than what is expected based on testing) and of course, the weather.  At this time, we do not know yet whether we will need to go into a third construction season in spring 2010.  Our priority is to make sure the work gets done carefully and completely, more so than keeping to the original schedule.  We will continue to provide construction information on this page as the 2009 season proceeds.

 
2) What about the traffic and the noise?

All reasonable effort is being made to keep the traffic on Throop Borough roads to a minimum; however as with any construction site, there will be trucks, workers' vehicles and the noise of the equipment on-site.  When we expect a period of high construction activity, with more than the usual amount of trucks and noise, we will tell people the expected dates on this page.

3) What will the working hours be?

Working hours will be from approximately 6:30 AM to 4:30 PM Monday through Friday (with the possibility of working until 7 pm when needed) and on Saturday, from approximately 6:30 AM to 2:30 PM. These days and times are consistent with Throop Borough ordinances.

 

502 George Street | Throop, PA 18512 | tel 570.383.9313 | fax 570.383.9309 | email layers@advancedgeoservices.com

Send mail to
agc@advancedgeoservices.com with questions or comments about this web site.
Copyright © 2006 Advanced GeoServices