|
| |
Construction Schedule and Information

Weekly Construction Schedule - December
19
through December 25, 2008
|
Weekly
Project
Schedule
&
Remediation Activities
Last
Updated: December 19, 2008
Holiday Schedule:
SCE will be off (no activities at the Marjol Site) for the Christmas
Holiday from Thursday, December 25, 2008 to Monday, December 29,
2008. There will be no work taking place during this time other
than inspections and air monitoring activities. SCE will work at
the Marjol Site from Monday, December 29, 2008 to Wednesday,
December 31, 2008. From December 29 through 31, 2008, only
maintenance and stabilization activities will be performed; no
excavation work will take place. SCE will then be off (no
activities at the Marjol site) from Thursday, January 1, 2009 to
Monday, January 5, 2009. Regular activities including excavation
work will resume on January 5, 2009.
Notes: Items that we think residents might be particularly
interested in are highlighted in
orange.
1) Due to the time of year, SCE will now be doing straw seeding
instead of hydro-seeding. Residents
may see dust from the straw in areas where the straw seeding is
taking place. The dust is not from
soil, but rather, from the straw.
2) Work in Areas U, T, and M
will be very visible to the community and close to residential
areas, so
residents will
see the equipment and hear the back up alarms and the sound of the
equipment running.
Due to the close proximity to the residential area, USEPA will have
a representative from the Army
Corps of Engineers on-site to observe these excavation activities
|
|
Period Covered: |
Planned Activities |
Expected Off-Site Impact |
|
December 19, 2008 to December 25, 2008
|
·
Place topsoil in and stabilize areas T and U.
·
Excavation and backfill of Areas M and J (front parking lot near
guard trailer).
·
Continue grinding tree stumps on-site. The wood chips are then
being used for stabilization purposes on the Site.
·
Backfilling of the final secondary fissure located in the North
Woods area
·
Stabilization (erosion control material and straw placement) of
excavated areas in the North Woods.
·
Stabilization (straw and wood chip placement) of all disturbed
areas on-site.
·
Contaminated material in the Containment (cap) Area will be
covered with clean soils.
|
·
This work will be very visible to the community and close to
residential areas, so residents will
see the equipment and hear the back up alarms and the sound of
the equipment running.
·
This work will be very visible to the community and close to
residential areas, so residents will
see the equipment and hear the back up alarms and the sound of
the equipment running.
·
Residents may hear the sound of the grinding machine. This
activity is noisy.
·
Residents may see the equipment and hear the back up alarms and
the sound of the equipment running.
·
Residents may see the equipment and hear the back up alarms and
the sound of the equipment running.
·
Residents may see the equipment and hear the back up alarms and
the sound of the equipment running.
·
Residents may see the equipment and hear the back up alarms and
the sound of the equipment running.
|
Construction Information
Here is some basic information that may answer
some of your important questions on how construction will affect those of you
living near the Marjol Site:
1) When will construction start and when
will it end?
The construction work began on May 12, 2008 and is expected to take until November 2009 to complete.
2)
What about the traffic and the noise?
All reasonable effort is being made to keep the
traffic on Throop Borough roads to a minimum; however as with any construction
site, there will be trucks, workers' vehicles and the noise of the equipment
on-site. When we expect a period of high construction activity, with more
than the usual amount of trucks and noise, we will tell people the expected
dates on this page.

3) What will the working hours be?
Working hours will be from 7 AM to 5 PM Monday
through Friday (with the possibility of working until 7 pm when needed) and on
Saturday, when necessary. These days and times are consistent with Throop
Borough ordinances.
Incident Report -
Discharge of Muddy Water Into Sulphur Creek - July 28, 2008
On July 28, 2008, muddy water was discharged from
the Marjol site into Sulphur Creek. The discharge lasted for about a half hour
to forty minutes and was in violation of site procedures. Fortunately, the water
that was discharged, although muddy, was from the new basin which is only
collecting water from areas of the Site that are not contaminated. AGC collected
two sediment samples at the location where the basin water discharges into
Sulphur Creek. The two samples had lead readings that were below the detection
limit of the instrument so there is no evidence of a release of
lead-contaminated sediment into the river. A sample was taken in the river for
confirmation following the protocols in the design but the results of the lead
analysis have not been received yet. Throop Borough also tested the sediments in
Sulphur Creek but those results aren’t available yet either.
Even though the discharge was from clean areas, the incident should not have
occurred, and Throop Borough should have been contacted sooner. These are both
significant errors that called for reconsideration of site procedures.
Gould voluntarily shut down construction operations at the Site on Wednesday,
July 30, 2008, in order that the incident which occurred could be properly
addressed. A meeting was held on Thursday, July 31, 2008, to discuss the
incident and develop a set of procedures such that this type of incident does
not happen again in the future. Representatives from Gould, AGC, SCE, PADEP,
USEPA, Throop Borough, Representative Frank Andrews Shimkus, and members of the
press were in attendance at the meeting.
At the meeting, AGC reviewed the measures that Gould, AGC and SCE proposed to
prevent any such incident from happening again.
● Directives to stop
an activity will be given visually as well as orally using a handwritten
“STOP”, flag or pre-determined signal.
● Daily
operational meetings will be held to discuss the next day’s work and develop
contingency plans in the event that something unexpected happens.
● If an
established procedure is modified, then a test run will be conducted to
ensure that the modified procedure will accomplish the objectives.
Changes were made on SCE’s on-site personnel as
well to improve internal communications and communications with AGC. Changes
were also made in AGC staffing and procedures at the site to emphasize the need
to inform Borough officials immediately of any unexpected event of possible
public concern.
Both USEPA and PADEP stated that they did not have a problem with work resuming
on Friday, August 1, 2008. PADEP required that a detailed report on the
incident be provided to it, and they are conducting their own investigation.
(Click here to review the NPDES non-compliance report on
the incident.) Throop Borough has been
provided a copy of the report.
(Click the dates below to read the recent articles and an editorial from the
Scranton Times.)
-
Article, July
30, 2008
-
Article, July
31, 2008
-
Article,
August 1, 2008
-
Editorial, August 1, 2008
Incident Report -
Communications Lapse and Above-Standard Dust Readings - August 4, 2008
On Monday, August 4, 2008, a communications lapse
occurred when the contractor (SCE) did not notify AGC that excavation of topsoil
over battery casings would occur. This excavation was performed to allow SCE to
pump water from the existing basin as allowed in the 100% Design. Even though
the action is something that is allowed, AGC needed to have air monitors set up
prior to movement of contaminated soils, so that the effectiveness of the dust
control measures could be monitored. The delay was very brief because AGC people
onsite saw the excavation and set up the monitors within minutes. Nonetheless,
this was the second communications lapse within a week, and shows that further
work is still needed on site communications.
In the daily operations meeting later on Monday (as well as in earlier
discussions after the excavation occurred), the importance of communicating
these types of changes in site activities was stressed.
When the air monitors were set up, the excavation was already completed and the
pumping of water was taking place. The air monitors recorded particulate matter
(e.g., dust) slightly in excess of the relevant performance standard for
excavation of battery casing material contained in the 100% Design. It was
determined that no corrective action was necessary based on several factors:
· The above-standard readings were observed prior to when the instrument was
fully stabilized, so they may not be representative of the actual conditions at
the time.
· There was no visible dust.
· The excavation had occurred through wet soils, decreasing the chance of dust
being released.
· The readings upwind of the excavation were also slightly elevated.
Review of the data at the end of the day indicated that there were some half
hour averages that were above the standard that were measured when there was no
excavation taking place, only pumping of water. The performance standard for
when battery casings are excavated is extremely low. As in this case, the
performance standard can
sometimes be below the level of dust in upwind samples – that is, dust having
nothing to do with site activities. So a brief reading that is over this
standard is neither unexpected nor alarming and may not warrant a change in how
work is being performed. It is a measure of the extreme care that will be taken
when excavating these materials. We are continuing to review the standards as
well as the equipment used to measure them and evaluating how the work is being
performed in order to complete the excavations in a safe manner.
Throop Borough was notified of both the communications lapse and the
above-standard dust readings.
Incident Report – Water Line Pierced – September 12, 2008
|
During construction activities at the Marjol Site today, when grubbing
(removing roots and grass) in an area along the Sulphur Creek side of
the Site, the water line that runs through the property was pierced.
Note: This water line was relocated in 1998 so that it runs outside the
area of contamination. The area where the line was pierced was a
clean (non-contaminated) area, so there was no threat of a release of
contaminated material at any time. Pennsylvania American Water
Company (PAWC) was on-site and shut the water line down before and after
the pierce location in order to repair the line. PAWC was able to
reroute water flow so that residents are not without water. Water
at the Site is turned off and PAWC will return on Monday, September 15,
2008 to do additional repair work.
|
|